中国海洋统计年鉴 2010,栏目:4 主要海洋产业生产能力>>4-7 主要潮汐电站分布情况,共1页
CAJ格式文件下载
PDF格式文件下载
Excel格式文件下载
|
|
4-7主要潮汐电站分布情况 |
| Distribution of Major
Tidal Power Stations |
| |
| |
|
装机容量 |
| 电站名称 |
运行情况 |
(千瓦) |
|
Name |
Status of operation |
Capacity |
| |
|
(kW) |
| |
|
|
| 江厦潮汐试验电站 |
*** |
*** |
| |
It began construction in 1970,was put
into use in |
|
| Jiangxia Experimental Tidal
Power Station |
1980,and has been in operation so
far. |
|
| 海山潮汐电站 |
*** |
*** |
| |
It began construction in 1972,was put
into use in |
|
| Haishan Tidal Power Station |
1 975,and has been in operation so
far. |
|
| 岳浦潮汐电站 |
*** |
|
| |
It began construction in 1
970,stopped power |
|
| Yuepu Tidal Power Station |
generation in 1978. |
|
| 白沙口潮汐电站 |
*** |
*** |
| |
It began construction in 1970,was put
into use in |
|
| Baishakou Tidal Power Station |
1978,and has been in operation so
far. |
|
| 果子山潮汐电站 |
已经投入前期筹备工作阶段,未确定开工时间。 |
|
| Guozishan Tidal Power Station |
It has been put into the first stage
of preparation,and |
|
| |